 |
|
|

|
Ford Motor Assembly Plant (Oakville, Ontario)
Description: Major tearout in Automotive Plant involving
removal of in excess of 135 chimneys and exhaust systems by helicopter.
|
|

|
Nordic Mine (Rio Algom, Elliot Lake, Ontario)
Nordic Mine was started 1955, closed 1986. Structures include boiler
plant, hoist, mill, warehouses, and storage facilities. Products
included uranium, thorium and yttrium. Duration of project including
site remediation was 8 months.
|
|

|
St. Lawrence Starch (Port Credit,
Ontario)
Plant site has been in operation since 1889. In addition to demolition
of all structures, excluding the historical main office, there included
the handling and disposal of significant levels of designated substances
such as asbestos, arsenic, lead, mercury, PCB's, liquid and solid
wastes. In addition, demolition included the felling of the 320
foot concrete stack by use of explosives. Duration of this project
was approximately 8 months.
|
|

|
Dow Chemical (Sarnia, Ontario)
Project involved the dismantling and removal of a 180 ft suspended
boiler in a fully operational chemical plant. Duration of the work
was approximately eight months with no lost time injuries. The entire
plant's electrical supply as well as natural gas lines ran adjacent
to the existing boilers.
|
|

|
Inco (Coppercliff,
Ontario)
Demolition of existing furnace building, including roasters, sample
house and runaround. Project involved removal of structures within
an operating environment on a very tight schedule. Project was completed
2 days in advance of deadline with no lost time injuries during
adverse winter weather conditions. Approximately 5,000 tons of scrap
steel was generated and shipped.
|
|

|
Arrowhead Metal (Etobicoke,
Ontario)
Complete demolition of 1.2 million square foot foundry and plant
in Etobicoke. Project involved asbestos, PCB waste containment and
storage, disposal of carbon block dust and contaminated soil and
brick. Project generated in excess of 10,000 tons of scrap steel
and over 200 tons of marketable copper scrap. Demolition was 18
months.
|
|

|
Stanrock Mine, Denison
Mines (Elliot Lake, Ontario)
Stanrock Uranium Mine and Mill was commissioned in March of 1958
with a designed mill capacity of 3,300 tons per day. Structures
include existing boiler plant, mill, hoist, concrete head frame
and assorted warehouses. Involved in the contract was the capping
of service raises and placing of rock fill plug at the entrance
to the adit. Problems associated with the project involved higher
than normal radiation contamination of building materials, equipment
and residual yelloweake on the floor of the mill. Duration of this
project was approximately 12 months.
|
|

|
Toronto Eaton Centre
(Toronto, Ontario)
Redevelopment of an entire city block comprising of over a dozen
major buildings over the course of two years. A project of this
size had never been undertaken in Toronto prior to and since. Close
co-ordination between Owner, City representatives and construction
crews allowed tight schedule to be met and costs to be within budget.
|
|

|
Stelco Steel - Hilton
Works (Hamilton, Ontario)
Two ore bridges, built in 1951 were demolished utilizing shaped
charges explosives. Each bridge measured over 1,000 feet long, were
160 feet high and weighed 3,500 tons. After bridges were dropped,
Hydraulic shears cut up steel into prepared scrap that was sold
to an adjacent mill. Duration of project was less than 3 months
|
|